The Dubai Metro Blue Line has reached 29% overall completion, according to the Dubai Media Office. His Highness Sheikh Hamdan bin Mohammed bin Rashid Al Maktoum, Crown Prince of Dubai, reviewed progress at the Blue Line worksite in Dubai Festival City on 22 November 2026, where the Roads and Transport Authority (RTA) also unveiled the new Blue Line train design. The 30 km line will link Mirdif, Al Warqa'a, International City, Dubai Silicon Oasis, Dubai Academic City, Dubai Festival City and Dubai Creek Harbour, and is scheduled to open on 9 September 2029.

Credit: Dubai Media Office
Construction Progress
| Work package | Completion |
|---|---|
| Overall project | 29% |
| Tunnel excavation | 55% |
| Bridge piers | 62% |
| Underground stations | 32% |
| Bridge works | 17% |
| Elevated stations | 16% |
Source: Dubai Media Office, 22 November 2026. More than 14,000 workers have contributed over 33 million working hours so far.
The project is being delivered by the MAPA–LIMAK–CRRC consortium. One of its biggest pieces is a 1.3 km bridge across Dubai Creek, the Metro's first Creek crossing, built from precast concrete segments placed from completed piers so that marine traffic keeps moving during construction.

Credit: Dubai Media Office
The Blue Line at a Glance
| Length | 30 km (15.5 km underground, 14.5 km above ground) |
|---|---|
| Stations | 14, including an iconic Emaar Properties station at Dubai Creek Harbour |
| Interchanges | Three: one with the Red Line, one with the Green Line, and one linking the line's two branches |
| Areas served | Mirdif, Al Warqa'a, International City, Dubai Silicon Oasis, Dubai Academic City, Dubai Festival City, Dubai Creek Harbour |
| Opening date | 9 September 2029 (RTA) |
| Contractor | MAPA–LIMAK–CRRC consortium |
The New Train Design
Each new Blue Line train has a design capacity of 675 passengers and a total capacity of 1,246 passengers per journey. Inside there are three sections: Gold Class, with a star-sky ceiling, wireless chargers and adaptive lighting; Silver Class; and a dedicated carriage for women and children. Smart cameras detect obstacles on the track and count passengers to monitor crowding in real time.

Credit: Dubai Media Office
Sheikh Hamdan also reviewed a new train systems simulation laboratory built with CASCO Signal, the first of its kind in the Middle East, which the RTA says will cut testing time by 85% and lift train punctuality accuracy above 99.7%, and ARIIS, an AI- and LiDAR-based system for inspecting rail infrastructure. Station interiors will follow five architectural concepts: the Emaar Properties station, inspired by a crossing gateway, and four designs based on water, air, fire and earth.

Credit: Dubai Media Office
Market Data: Apartments Along the Blue Line
| Area (apartments) | Median price (AED) | Median AED per sq ft | Price change | Sales volume | Median rent (AED/yr) | Gross yield |
|---|---|---|---|---|---|---|
| International City | 650,000 | 680 | -5.5% | 25 | 46,000 | 9% |
| Dubai Silicon Oasis | 880,000 | 1,170 | +0.2% | 1,333 | 54,000 | 8% |
| Mirdif | 1,785,000 | 1,210 | -5.4% | 142 | 64,000 | 6% |
| Dubai Creek Harbour | 2,650,000 | 2,550 | +4.6% | 3,669 | 130,000 | 7% |
Source: DXBinteract (Dubai Land Department transaction data), as of November 2026. Reporting windows may differ by metric. The International City figure covers the Al Warsan First sub-area.
Why It Matters for Property
Metro access is one of the few things that reliably lifts demand for a neighbourhood, and the Blue Line brings it to districts that have relied on cars until now. International City, Dubai Silicon Oasis and Mirdif offer some of Dubai's highest gross yields at relatively low entry prices, and a confirmed 2029 metro link strengthens their long-term case with tenants who commute. At the other end, Dubai Creek Harbour gets its own iconic station and a direct link across the Creek. The RTA also says the line supports the Dubai 2040 Urban Master Plan by encouraging development around stations, so expect more launches marketed on Blue Line proximity. Check the actual walking distance to the nearest planned station rather than relying on marketing claims.
Talk to Luxwell Real Estate
Luxwell Real Estate's Dubai property experts can shortlist ready and off-plan homes near planned Blue Line stations and compare yields across Dubai Silicon Oasis, International City, Mirdif and Dubai Creek Harbour.
- Call: +971 50 856 2749
- WhatsApp: +971 50 856 2749
- Email: info@luxwellrealestate.com
- Contact form: Contact Luxwell
Sources: Dubai Media Office (22 November 2026); Roads and Transport Authority; DXBinteract.
Related Reading
Frequently Asked Questions
How far along is the Dubai Metro Blue Line?
- Overall completion reached 29% as of 22 November 2026, with tunnel excavation at 55%, bridge piers at 62%, underground stations at 32%, bridge works at 17% and elevated stations at 16%, according to the Dubai Media Office.
When will the Blue Line open?
- The RTA has scheduled the Blue Line to open on 9 September 2029.
Which areas will the Blue Line serve?
- Mirdif, Al Warqa'a, International City, Dubai Silicon Oasis, Dubai Academic City, Dubai Festival City and Dubai Creek Harbour, across 30 km and 14 stations.
How does the Blue Line connect to the rest of the Metro?
- It has three interchange stations: one with the Red Line, one with the Green Line, and one linking the Blue Line's two branches.
What is new about the Blue Line trains?
- The new trains carry up to 1,246 passengers per journey and have Gold Class, Silver Class and a carriage for women and children, plus smart cameras that detect track obstacles and monitor crowding.
Will the Blue Line affect property prices?
- Metro access usually supports rental demand and resale interest. Areas on the line such as International City, Dubai Silicon Oasis and Mirdif already have gross yields of 6% to 9% in DXBinteract data. Check the real walking distance to the nearest station before buying.
Request details
Leave your details to download the details